Japan's JERA is in talks with Anthropic, Meta and other US tech firms to build data centres beside its power plants
JERA's chief told Nikkei the group is negotiating 'behind the meter' sites around Tokyo, including at the Chiba Thermal Power Station, and FirstSquawk relays that Amazon, Microsoft and Google are also in talks; no contract, size or price has been announced.
Why it matters
Power, not chips, is becoming the limiting factor for AI capacity, and Japan's largest electricity producer is offering sites where data centres draw power directly from a plant rather than waiting for grid connections. If Anthropic or Meta sign, it would be among the first large frontier-lab compute commitments sited at a Japanese power station. The talks follow similar co-location deals in the US. Watch for named partners, megawatt figures and whether regulators accept behind-the-meter supply around Tokyo.
Key facts
- JERA is Japan's largest electricity producer
- Talks with Anthropic, Meta and other US tech firms (Nikkei)
- Amazon, Microsoft and Google also in discussions (FirstSquawk, citing Nikkei)
- 'Behind the meter' sites around Tokyo
- Planned site at Chiba Thermal Power Station
- No contract terms announced