Norway's grid operator Statnett pauses new grid capacity reservations for data centres until August 2027

Statnett file photo of high-voltage transmission lines in a winter landscape in Norway
Statnett

Statnett says data centres' fast, software-driven load swings threaten safe system operation; existing connections and already approved sites are not affected.

Read at Statnett Share

Why it matters

Norway has been one of Europe's favoured locations for AI data centres because of its cheap hydropower, so a halt by the national grid operator is a real constraint on the build-out. Statnett says 800 MW of data centres is connected today, 4,200 MW has reserved capacity, 9,100 MW is in the queue and requests cover a further 18,000 MW, against peak national demand of just over 25,000 MW. The pause is expected to be lifted by 1 August 2027 at the latest. Watch for the technical requirements Statnett develops in the meantime and the government's planned licensing scheme for data centres.

Key facts

  • 800 MW of data centres connected
  • 4,200 MW reserved, 9,100 MW queued
  • Requests for a further 18,000 MW
  • Norway peak demand just over 25,000 MW
  • Pause expected to end by 1 August 2027
  • Existing connections not affected