Spain approves decree requiring large data centres to prove 80% of their power comes from new renewables

Generic file photo of server racks in a data centre.
BalticServers.com, CC BY-SA 3.0, via Wikimedia Commons

The royal decree covers centres above 10 MW, matches consumption hour by hour and lets near-term projects phase in from 60% at peak hours; Minister Sara Aagesen says without it bills would rise by €5bn a year.

Read at MITECO (Spanish government) Share

Why it matters

Spain is one of Europe's main targets for new AI data centres, and the decree applies to them the hourly-matching and additionality test Spain already uses for renewable hydrogen. The 80% must come from renewable plants connected no more than 36 months before the centre starts, so it forces new generation rather than buying existing supply. El Español reports much of the industry opposed it. All centres must meet 80% with hourly matching from 1 January 2032. It takes effect on publication in the official gazette.

Key facts

  • Applies to data centres above 10 MW
  • 80% renewable, matched hour by hour
  • Renewables must connect at most 36 months before the centre
  • Transitional regime: 60% at peak hours until 31 December 2028, then 70%
  • All centres must meet 80% from 1 January 2032
  • Aagesen: €5bn a year in extra bills without the decree